Earned Value Mindset

Earned Value Mindset

Why do we need to establish earned value metrics based on both cost and manhours? Why do we need to develop a cost and resource-loaded schedule? If your answer is something like:

  • Because it is a part of the contract or the client's requirements.
  • Because it is a part of my company's procedures.

Then you don't fully take advantage of the earned value applications in project control. This article will explain the mindset behind the cost and resources loaded schedule as well as the associated applications. The term "cost" might mean different things based on the context. In this article, I will assume the case in which we use a schedule to manage a contract, while we make the necessary reporting and submissions to an Engineer or client. For simplicity, the term "cost" that I refer to is the budgeted total cost which is based on the BOQ rate. It is the amount that we use to load the schedule and derive the earned value from it.

Why do we need a cost and resource-loaded schedule?

One obvious reason why we develop such a schedule is to see future cost and manhours forecasts but there is more to that. In the below image, assume that there are two activities A & B in the project. Each activity has a 5-day duration.

No alt text provided for this image

If activity A is completed and activity B hasn't started yet, what is the overall project % complete? Your first intuitive answer would be 50%. But what if activity A is a concrete activity that is worth $9,000 and activity B is a housekeeping activity that is worth $1,000? In this case, the overall actual % is 90%. Another example might be a procurement activity that has 90 days duration but costs $10,000 and a concrete activity that has a 1-day duration but costs $30,000. hence, we can make two conclusions based on the above.

1- We can't use time as a weighting system to evaluate performance. However, there are other approaches such as CPM that evaluate the time intensity and the project criticality levels.

2- Cost can be an effective weighting system to measure progress.

Why isn't cost enough to evaluate performance?

As per the above example, the cost seems very effective to measure progress. Why do we need to report the Planned vs Actual %, Variance % and SPI as per manhours too? Because some activities are very costly, while others are more labor intensive. For example, a concrete activity costs a lot of money but might require 15 man-days over a 1-day duration. On the other hand, paint activity costs a lot less but might require 60 man-days to execute the work. Therefore, we need to measure progress from both perspectives. You can refer to the below image to understand the concept better.

No alt text provided for this image

Another example to demonstrate the concept can be seen prior to the project completion. it is very common to see the below scenario:

1- The project is completed 95% (cost-wise) because most activities have been completed and all major costly materials have been delivered and installed onsite.

2- The project is completed 85% (man-hour wise) because there is a lot of pending snagging, paint, testing and final touch-ups which are more labor-demanding.

That's why we need to have a cost and resource-loaded schedule to serve as both forecasting weighting tools. Moreover, it is essential to report progress as per both cost and manhours.

Regards,

Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

Michaelangelo Dioquino COPC® CPM,CLSSBB

Customer Service Professional|Facility Management Planning and Performance|Quality Assurance|Property Management|Continuous Improvement Specialist|Certified Lean Six Sigma Black Belt|COPC Certified Professional Manager|

1y

Power Bi course please. Thanks

Ahmad Banat

Project Manager | Aramco Stadium | Expertise in Project Management | PMP®, PMI-RMP®

1y

Simple and valuable 🙏🏼🙏🏼

Eng. Shahmi Nilamdeen

Planning Engineer | Certified in Primavera P6 & BIM | Royal Commission Approved | SCE Registered

1y

Great article. Well explained.

Theresa Ugiagbe

Transformational Business Analyst | Agile | Waterfall | Stakeholder Management| Process Optimisation | SMS Aggregator|Requiremet Gathering| Driving Innovation in Telecoms| Healthcare, and HR

1y

Thanks for sharing

To view or add a comment, sign in

More articles by Osama Saad, MBA, PMP, PSP, CCP, PMI-SP

  • 20 ways to show mitigation for excusable delay

    20 ways to show mitigation for excusable delay

    When planning engineers conduct delay analysis and prepare an extension of time claims, they often face confusion about…

    18 Comments
  • Excusable delay mitigation in EOT claims

    Excusable delay mitigation in EOT claims

    Most modern contracts require the contractor to "mitigate" the delays even though such delays are beyond its reasonable…

    11 Comments
  • Longest Path vs Critical Path

    Longest Path vs Critical Path

    Many planning engineers experience confusion regarding the difference between the longest path and the critical path…

    14 Comments
  • Managing Schedule Delays

    Managing Schedule Delays

    How should we manage the schedule delays? Should we make regular schedule changes to ensure that the schedule updates…

    19 Comments
  • Schedule Changes - Explained

    Schedule Changes - Explained

    Schedule changes are crucial in project control but they are not often discussed. You most likely need to make…

    13 Comments
  • Certified Cost Professional (CCP) - The Ultimate Guide

    Certified Cost Professional (CCP) - The Ultimate Guide

    The Certified Cost Professional (CCP) certification is one of the most widely recognized certificates in the Project…

    12 Comments
  • PMI-Scheduling Professional (PMI-SP) Certification - The Ultimate Guide

    PMI-Scheduling Professional (PMI-SP) Certification - The Ultimate Guide

    PMI-Scheduling Professional (PMI-SP) is one of the most widely recognized certificates for Planning Engineers in the…

    14 Comments
  • PSP vs PMI-SP for Planning Engineers

    PSP vs PMI-SP for Planning Engineers

    PSP and PMI-SP are the most widely recognized certificates in the planning field. However, many planning engineers…

    26 Comments
  • 3 challenges in the PSP exam preparation

    3 challenges in the PSP exam preparation

    PSP is one of the most widely recognized certificates for planning engineers. If you are a bachelor's degree holder and…

    1 Comment
  • 8 Myths of Power BI in Project Control

    8 Myths of Power BI in Project Control

    Although Power BI is a great tool, there are many false beliefs about its applications in project control. As a result,…

    5 Comments

Insights from the community

Others also viewed

Explore topics